Bellefonte Nuclear Generating Station - Wikipedia
src: upload.wikimedia.org

The Bellefonte Nuclear Generating Station (shortly BLN) is a partially constructed nuclear power plant located in Hollywood, Alabama. A total of four nuclear reactors (two originally; and two of new designs), have been proposed for the site over a 40-year period, with over $4 billion having been spent (constructing the preliminary plant infrastructure and ordering/delivering/installing major equipment items. But no nuclear reactor nor electric generating plant was ever nearly completed; and no nuclear fuel was delivered or loaded. Meaningful construction progress at the site site was halted in 1988. Starting after its termination in 2005, TVA implemented an investment recovery effort to recoup some of the costs associated with Bellefonte. As part of the investment recovery effort, all or parts of some major plant components, including steam generators, feedwater heaters, large pumps and motors, demineralized water and condensate storage tanks, main condenser tubes, and some piping and valves were removed and sold. Additionally, some usable components were transferred from Bellefonte to other TVA facilities as spares.


Video Bellefonte Nuclear Generating Station



Units 1 and 2

The Bellefonte Nuclear Generating Station site is owned by the Tennessee Valley Authority and is located in Hollywood, Alabama. The two partially built 1,256 megawatt (MWe) pressurized water reactors on the site were made by Babcock & Wilcox and are called a 205 design due to the number of fuel assemblies in the core. These units are of the same design as WNP-1 which is also unfinished, and as the Mülheim-Kärlich A reactor in Germany that operated for three years and proved the design.

Reactor Unit 1 construction was estimated at 88%  complete (mechanical - nuclear island) and Unit 2 construction was estimated 58% complete (mechanical - nuclear island) when TVA's Board suspended the project; and the plants' construction in 1988, after a combined $6 billion investment. Subsequent asset recovery activities (i.e., the removal (without ordering or planning for replacement), of useable equipment and systems to other TVA power plant sites), along with more recent (2000s) inspections of the operable state of remaining equipment, resulted in BLN 1&2 now being considered approximately 55 percent and 35 percent complete (mechanical - nuclear island only) respectively.

Should completion of either of the units be decided upon, the experience in completing Watts Bar Unit 2 is instructive in both time to completion, and magnitude of the scope of the work. All of the remaining major equipment items delivered, installed, and not later removed, will have to be baseline reexamined for use in a design which will have to conform to standards and experience gained as a consequence of both major accidents and natural disasters that have occurred in the thirty-eight plus years since construction was initially begun. Each unit would require almost a decade to complete in amended design, detailed engineering, construction, validation, and testing, thru initial operations. The exact total cost of such an effort would also be unknown as the detailed design to meet the current "lessons learned" standards of design is not yet completed; and thus, the scale and scope of construction to initial operations (upon which the cost estimate would be based) is unknown.

Although the construction permits were terminated on September 15, 2006, TVA investigated the completion of these first two units with operation projected to start Unit 1 in 2017 and Unit 2 in 2021. In August 2008 TVA asked the NRC to reinstate the construction permits as part of the restart evaluation. This request was granted by the NRC on February 9, 2009, albeit as a terminated application which required significant inspection of all systems to bring the license to the deferred stage. The status was upgraded January 14, 2010 to deferred.


Maps Bellefonte Nuclear Generating Station



Units 3 and 4

On September 22, 2005 it was announced that Bellefonte was also selected as the site for one or two AP1000 pressurized water reactors to be called Units 3 and 4. TVA filed the necessary applications in November 2007 to begin the design and construction process. For details, see Nuclear Power 2010 Program.

In August 2009, the Tennessee Valley Authority, faced with "falling electric sales and rising costs from cleaning up a massive coal ash spill in Tennessee", trimmed plans for the potential four-unit Bellefonte nuclear plant to one reactor.


Bellefonte Nuclear Plant Going to Auction - Power Engineering
src: www.power-eng.com


Later developments

On August 20, 2010 the TVA Board of Directors authorized $248 million to continue development of the Bellefonte Unit 1. On August 18, 2011, the TVA board of directors voted to move forward with the construction of the unit one reactor at Bellefonte.

In 2011, TVA approved a plan to restart construction of the Bellefonte Unit 1 reactor, dependent on work at another reactor TVA completing - Watts Bar 2 in Tennessee. In December 2012, TVA said the Watts Bar 2 project is on schedule to finish in December 2015.

TVA again announced staffing cuts at the plant in June 2013, reducing staffing at the plant from 540 to approximately 140.

In October 2013, it was announced that former TVA Chairman Dennis Bottorff and financier Franklin L. Haney have drafted a proposal to finish the Bellefonte Nuclear Plant using private funds and federal tax credits.

Sale of site

In 2015 TVA determined that it would be unlikely to need a large plant like Bellefonte for the next 20 years, and in May 2016 elected to declare the plant surplus, and sell the 1,600 acre site at auction for a minimum price of $36.4 million.

On October 14, 2016, TVA directors declared the unfinished nuclear plant to be surplus property and set a November 14, 2016 auction date to sell the unfinished plant and property. Nuclear Development LLC, led by Chattanooga-based developer Franklin L. Haney, purchased the Bellefonte Nuclear Plant at auction with a winning bid of $111 million, three times the minimum bid of $36.4 million; Nuclear Development intends to complete the two units at a projected additional investment of over $13 billion. Haney's bid beat the only other bidder, Jackson Holdings of Alabama LLC, which was hoping to use components from the unfinished plant for a reactor under construction in India. Another prospective bidder, Phoenix Energy of Nevada, was unable to complete their financing arrangements in time to place a bid. Construction is expected to start by the end of 2018 and take approximately five years to complete. It will require a construction crew of between 5000 and 7000.


Bellefonte Nuclear Generating Station - Wikiwand
src: upload.wikimedia.org


Reactor data

The Bellefonte Generating Station consisted of four cancelled reactors.


Date Set for Bellefonte Plant Auction | Alabama Public Radio
src: mediad.publicbroadcasting.net


References


File:Bellefonte aerial.jpg - Wikimedia Commons
src: upload.wikimedia.org


External links

  • Bellefonte Image Gallery on Nukeworker website
  • http://edocket.access.gpo.gov/2009/E9-19045.htm